Release – Century Lithium Updates Progress on Testing With Koch Technology Solutions

Research News and Market Data on CYDVF

August 9, 2023 – Vancouver, Canada – Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (Century Lithium or the Company) is pleased to report successful progress in its collaboration with Koch Technology Solutions (KTS), a Koch Engineered Solutions (KES) company. As reported previously (see April 17, 2023, news release) Century Lithium and KTS are working together on the application of KTS’s Li-ProTM system at Century’s Lithium Extraction Facility (Pilot Plant) in Amargosa Valley, Nevada, USA.

“Century Lithium is delighted to see the progress made in our collaboration with Koch Technology Solutions” stated Bill Willoughby, President, and CEO of Century Lithium. “Our team, with KTS’s input has successfully incorporated and operated the equipment at our Pilot Plant with significantly improved results.”

Since October 2021, Century Lithium has been continuously testing the extraction of lithium from the claystone found at its 100%-owned Clayton Valley Lithium Project (Project) in Nevada utilizing a chloride-based leaching process. Testing of the Li-ProTM system was conducted to evaluate potential improvements in the direct lithium extraction (DLE) area of the Pilot Plant.

Adam Sackett, President of Koch Technology Solutions, added, “The steady state results generated onsite with the Koch Technology Solutions Li-Pro™ Direct Lithium Extraction process has hit all our key milestones for the Century pilot program. We are excited to move towards engineering and executing a Li-Pro™ installation with commercial process guarantees.”

With the integration of KTS’s DLE process, the grades of the intermediate lithium solution produced at the Pilot Plant have increased to the highest levels to date, with an average grade of 7.5 grams/liter (g/l) (7,500 parts per million) lithium. These lithium concentrations are four times higher than previously generated, with sodium concentrations almost an order of magnitude lower.

Highlights To Date

  • Successful installation and operation of Koch’s Li-ProTM DLE process
  • Li-ProTM plant achieved steady state using Century Lithium’s chloride leaching process
  • Manufacture intermediate solutions with lithium grades of 7 to 8 g/l concentrations with average lithium to sodium ratios of 0.9 to 1.1
  • No observed degradation of media or accumulation of deleterious elements

Operational Results

Since the installation of KTS’s DLE equipment, Century Lithium has focused on improvements related to the operational aspects of the Pilot Plant and adjustments to the final flowsheet. These improvements were well supported through the development and incorporation of KTS’s DLE equipment at the Pilot Plant.

Century Lithium, with the support of KTS, has identified techniques to improve lithium recovery within the DLE area while minimizing deleterious elements in the final solutions. Collaboration between Century Lithium and Koch staff is very productive, generating ideas and changes that have resulted in the complete removal of calcium and magnesium, and marked reduction of sodium and potassium in the product solutions.

Qualified Person

Todd Fayram, MMSA-QP is the qualified person as defined by National Instrument 43-101 and has approved the technical information in this release.

About Century Lithium Corp.

Century Lithium Corp. (formerly Cypress Development Corp.) is an advanced stage lithium company, focused on developing its 100%-owned Clayton Valley Lithium Project in west-central Nevada, USA. Century Lithium is currently in the pilot stage of testing on material from its lithium-bearing claystone deposit at its Lithium Extraction Facility in Amargosa Valley, Nevada and progressing towards completing a Feasibility Study and permitting, with the goal of becoming a domestic producer of lithium for the growing electric vehicle and battery storage market.

ON BEHALF OF CENTURY LITHIUM CORP.
WILLIAM WILLOUGHBY, PhD., PE
President & Chief Executive Officer

For further information, please contact:
Spiros Cacos | Vice President, Investor Relations
Direct: +1 604 764 1851
Toll Free: 1 800 567 8181
scacos@centurylithium.com
centurylithium.com

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.

Cautionary Note Regarding Forward-Looking Statements

This release includes certain statements that may be deemed to be “forward-looking statements”. Forward-looking statements are subject to risks, uncertainties and assumptions and are identified by words such as “expects,” “estimates,” “projects,” “anticipates,” “believes,” “could,” “scheduled,” and other similar words. All statements in this release, other than statements of historical facts, that address events or developments that management of the Company expects, are forward-looking statements. Although management believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance, and actual results or developments may differ materially from those in the forward-looking statements. The Company undertakes no obligation to update these forward-looking statements if management’s beliefs, estimates or opinions, or other factors, should change. Factors that could cause actual results to differ materially from those in forward-looking statements, include market prices, exploration, and development successes, continued availability of capital and financing, and general economic, market or business conditions. Please see the public filings of the Company at www.sedar.com for further information.

Release – Century Lithium Appoints New Director

Research News and Market Data on CYDVF

July 17, 2023 – Vancouver, Canada – Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (“Century Lithium” or “the Company”) is pleased to announce the appointment of Dr. Corby G. Anderson to its Board of Directors, effective July 14, 2023.

Dr. Anderson is a Licensed Professional Chemical Engineer with over 40 years of global experience in engineering, design, industrial plant operations, corporate level management, education, research, and professional service. He holds degrees of BSc in Chemical Engineering from Montana State University, an MSc in Metallurgical Engineering from Montana Tech, and a PhD in Mining Engineering and Metallurgy from the University of Idaho. He most recently assisted Century Lithium as its Technical Advisor, Metallurgy.

“We are pleased to welcome Dr. Anderson to the Company’s Board of Directors” said Bryan Disher, Chair of Century Lithium. “As Technical Advisor, Dr. Anderson has been instrumental in the advancement of our Clayton Valley Lithium Project, and we look forward to his continued contribution to the Company in his new role on the Board of Directors”.

About Century Lithium Corp.

Century Lithium Corp. (formerly Cypress Development Corp.) is an advanced stage lithium company, focused on developing its 100%-owned Clayton Valley Lithium Project in west-central Nevada, USA. Century Lithium is currently in the pilot stage of testing on material from its lithium-bearing claystone deposit at its Lithium Extraction Facility in Amargosa Valley, Nevada and progressing towards completing a Feasibility Study and permitting, with the goal of becoming a domestic producer of lithium for the growing electric vehicle and battery storage market.

ON BEHALF OF CENTURY LITHIUM CORP.
WILLIAM WILLOUGHBY, PhD., PE
President & Chief Executive Officer

For further information, please contact:
Spiros Cacos | Vice President, Investor Relations
Direct: +1 604 764 1851
Toll Free: 1 800 567 8181
scacos@centurylithium.com 
centurylithium.com  

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.

Cautionary Note Regarding Forward-Looking Statements

This release includes certain statements that may be deemed to be “forward-looking statements”. Forward-looking statements are subject to risks, uncertainties and assumptions and are identified by words such as expects,” “estimates,” “projects,” “anticipates,” “believes,” “could,” “scheduled,” and other similar words. All statements in this release, other than statements of historical facts, that address events or developments that management of the Company expects, are forward-looking statements. Although management believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance, and actual results or developments may differ materially from those in the forward-looking statements. The Company undertakes no obligation to update these forward-looking statements if management’s beliefs, estimates or opinions, or other factors, should change. Factors that could cause actual results to differ materially from those in forward-looking statements, include market prices, exploration, and development successes, continued availability of capital and financing, and general economic, market or business conditions. Please see the public filings of the Company at www.sedar.com for further information.

Century Lithium Corp. (CYDVF) – From Nevada Claystone to Battery Grade Lithium Carbonate


Friday, May 26, 2023

Mark Reichman, Managing Director, Equity Research Analyst, Natural Resources, Noble Capital Markets, Inc.

Refer to the full report for the price target, fundamental analysis, and rating.

Consistency is key. Century Lithium produced lithium carbonate grading 99.87% from lithium-bearing claystone sourced from its Clayton Valley Lithium project. Several kilograms of high purity lithium carbonate were made from lithium solution produced at Century’s pilot lithium extraction facility. Following leaching and direct lithium extraction at the pilot plant, solutions were shipped to Saltworks Technologies Inc. for final processing. The results were in line with those reported in September 2022 when lithium carbonate grading 99.94% was produced.

Feasibility study expected in 2H 2023. The Clayton Valley feasibility study is expected to be completed in the second half of 2023. Major areas of the study are finished and estimates for capital and operating cost estimates have been received, including those for the chlor-alkali plant portion of the project. The estimates are being consolidated and reviewed, along with opportunities for further optimization and cost reduction.


Get the Full Report

Equity Research is available at no cost to Registered users of Channelchek. Not a Member? Click ‘Join’ to join the Channelchek Community. There is no cost to register, and we never collect credit card information.

This Company Sponsored Research is provided by Noble Capital Markets, Inc., a FINRA and S.E.C. registered broker-dealer (B/D).

*Analyst certification and important disclosures included in the full report. NOTE: investment decisions should not be based upon the content of this research summary. Proper due diligence is required before making any investment decision. 

Release – Century Lithium Reconfirms Production Of Battery Grade Purity Lithium Carbonate And Provides Update On Feasibility Study

Research News and Market Data on CYDVF

May 25, 2023 – Vancouver, Canada – Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (Century Lithium or the Company) is pleased to report it has repeated the production of a high-purity lithium carbonate (Li2CO3) grading 99.87% with lithium-bearing claystone from the Company’s 100%-owned Clayton Valley Lithium Project (Project) in Nevada, USA. Several kilograms of the high purity Li2CO3were made from the intermediate lithium solutions generated in January at the Company’s Lithium Extraction Facility (Pilot Plant) in Amargosa Valley, Nevada. Following leaching and direct lithium extraction (DLE) at the Pilot Plant, solutions were shipped to Saltworks Technologies Inc. (Saltworks) where the final processing was completed.

“These results are in line with those we reported in September 2022, when we achieved a significant milestone in making lithium carbonate grading 99.94%” stated Bill Willoughby, President and CEO of Century Lithium. “The latest results confirm our ability to obtain a high purity lithium product with a low level of impurities from our claystone process.”

Century Lithium has now successfully repeated steps from test mining through to the manufacture of battery-grade Li2CO3. The table below is a comparison of the latest results with those from September 2022. Also shown, are the constituent levels for battery grade lithium carbonate as published by two major producers. The results for the Company’s lithium carbonate material assays were finalized by Saltworks and SGS Canada Inc.

  Century Li2CO3 May 2023Century Li2CO3 September 2022Reference Source 1Reference Source 2
Li2CO3wt%99.87599.94>99.5>99.5
H2Owt%0.030.01<0.2<0.5
Nawt%0.0470.02<0.03<0.05
Cawt%0.0090.02<0.01<0.04
FeWppm31510<5
AlWppm<2610<10
CuWppm<4<410<5
NiWppm<5<510<6
Clwt%0.008%0.008%<0.01%<0.01%

Scroll right to view more 

Notes: wt% (weight percent), wppm (weight parts per million), calculated Li2COpurity based on sum of impurities measured above detection limit
Source 1 & 2: public company’s published composition of battery grade Li2CO,

Feasibility Study Update

A Feasibility Study on the Project (Study) began in February 2022, with the engagement of Wood PLC as independent lead author. The Study has progressed well, with contributions from Global Resource Engineers, WSP USA Environment & Infrastructure Inc., and thyssenkrupp nucera, and with the support of Century Lithium’s personnel and consultants.

Major areas of the Study are completed and estimates for capital and operating cost estimates received, including those for the chlor-alkali plant portion of the Project. Wood is in the process of consolidating the estimates and reviewing them with Century, along with evaluating further optimization and opportunities for cost reductions. This optimization work will extend beyond the previously estimated mid-year completion date for the Study. The Company continues to focus on the Study and will provide updates in due course.

At the Pilot Plant, the collaboration of Century Lithium and Koch Technology Solutions (KTS) is underway testing the KTS Li-Pro™ process for DLE. Century Lithium personnel are working closely with KTS in the testing program, which has now completed its third 7-day cycle of operation. Thus far, the KTS process equipment has operated exceptionally well, using feed solution from the Pilot Plant, and the Company is very pleased with its performance.

Qualified Person

Todd Fayram, MMSA-QP and Daniel Kalmbach, CPG, are the qualified persons as defined by National Instrument 43-101 and have approved the technical information in this release.

About Century Lithium Corp.

Century Lithium Corp. (formerly Cypress Development Corp.) is an advanced stage lithium company, focused on developing its 100%-owned Clayton Valley Lithium Project in west-central Nevada, USA. Century Lithium is currently in the pilot stage of testing on material from its lithium-bearing claystone deposit at its Lithium Extraction Facility in Amargosa Valley, Nevada and progressing towards completing a Feasibility Study and permitting, with the goal of becoming a domestic producer of lithium for the growing electric vehicle and battery storage market.

ON BEHALF OF CENTURY LITHIUM CORP.
WILLIAM WILLOUGHBY, PhD., PE
President & Chief Executive Officer

For further information, please contact:
Spiros Cacos | Vice President, Investor Relations
Direct: +1 604 764 1851
Toll Free: 1 800 567 8181
scacos@centurylithium.com
centurylithium.com  

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.

Cautionary Note Regarding Forward-Looking Statements

This release includes certain statements that may be deemed to be “forward-looking statements”. Forward-looking statements are subject to risks, uncertainties and assumptions and are identified by words such as expects,” “estimates,” “projects,” “anticipates,” “believes,” “could,” “scheduled,” and other similar words. All statements in this release, other than statements of historical facts, that address events or developments that management of the Company expects, are forward-looking statements. Although management believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance, and actual results or developments may differ materially from those in the forward-looking statements. The Company undertakes no obligation to update these forward-looking statements if management’s beliefs, estimates or opinions, or other factors, should change. Factors that could cause actual results to differ materially from those in forward-looking statements, include market prices, exploration, and development successes, continued availability of capital and financing, and general economic, market or business conditions. Please see the public filings of the Company at www.sedar.com for further information.

Century Lithium Corp. (CYDVF) – Moving Right Along


Wednesday, April 26, 2023

Mark Reichman, Managing Director, Equity Research Analyst, Natural Resources, Noble Capital Markets, Inc.

Refer to the full report for the price target, fundamental analysis, and rating.

Feasibility study expected by mid-year. The Clayton Valley feasibility study is advancing and expected to be released mid-2023. The main categories of work outstanding are: 1) project execution plan and schedule, 2) draft estimates, 3) draft report, 4) final capital and operating cost estimates, 5) final engineering report, and 6) final technical report. The feasibility study is being led by Wood PLC, supported by Global Resource Engineering for the mining component, thyssenKrupp Nucera AG & Co. for the design of the chlor-alkali plant, and Saltworks for the extraction process.

Collaboration with Koch. Apart from the feasibility study, Century Lithium is collaborating with Koch Technology Solutions (KTS) in the application of its proprietary Li-Pro direct lithium extraction (DLE) process. Koch Engineered Solutions, the owners of the Lionex direct lithium extraction technology, will provide the engineering design and costs for the full-scale DLE portion of the processing plant for the Clayton Valley Project.


Get the Full Report

Equity Research is available at no cost to Registered users of Channelchek. Not a Member? Click ‘Join’ to join the Channelchek Community. There is no cost to register, and we never collect credit card information.

This Company Sponsored Research is provided by Noble Capital Markets, Inc., a FINRA and S.E.C. registered broker-dealer (B/D).

*Analyst certification and important disclosures included in the full report. NOTE: investment decisions should not be based upon the content of this research summary. Proper due diligence is required before making any investment decision. 

Release – Century Lithium Provides Update On Collaboration With Koch Technology Solutions

Research News and Market Data on CDYVF

April 17, 2023 – Vancouver, Canada – Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (“Century Lithium” or “the Company”) is pleased to report that further to its news release dated February 9, 2023, the Company has received from Koch Technology Solutions’ (“KTS”) equipment for KTS’ Li-Pro™ process for direct lithium extraction (“DLE”). The KTS equipment has been installed and is now operating at Century Lithium’s Lithium Extraction Facility (“Pilot Plant”) in Amargosa Valley, Nevada, USA.

The collaboration between Century Lithium and KTS begins a field trial of KTS’ Li-Pro™ equipment to treat the process solutions generated at the Pilot Plant in the leaching of bulk sample claystone collected from the Company’s Clayton Valley Lithium Project (“Project”). Following successful installation, operation of KTS’ equipment went very well throughout an initial 7-day start-up.  Results from the program will enable KTS to provide engineering and cost data to Century Lithium for a full-scale installation of the DLE plant in Century Lithium’s Project.

About Koch Technology Solutions

Koch Technology Solutions (KTS) is the technology licensing business of Koch Engineered Solutions (KES). KTS creates value for its customers across a growing portfolio of technologies including direct lithium extraction, the polyester value chain, refining industry and 1,4-Butanediol plus its derivatives. KTS combines its exclusive technologies, expertise, and capabilities with those of other KES companies to provide overall solutions to optimize customers’ capital investments and existing manufacturing assets.

About Century Lithium Corp.

Century Lithium Corp. (formerly Cypress Development Corp.) is an advanced stage lithium company, focused on developing its 100%-owned Clayton Valley Lithium Project in west-central Nevada, USA. Century Lithium is currently in the pilot stage of testing on material from its lithium-bearing claystone deposit at its Lithium Extraction Facility in Amargosa Valley, Nevada and progressing towards completing a Feasibility Study and permitting, with the goal of becoming a domestic producer of lithium for the growing electric vehicle and battery storage market.

ON BEHALF OF CENTURY LITHIUM CORP.
WILLIAM WILLOUGHBY, PhD., PE
President & Chief Executive Officer

For further information, please contact:
Spiros Cacos | Vice President, Investor Relations
Direct: +1 604 764 1851
Toll Free: 1 800 567 8181
scacos@centurylithium.com 
centurylithium.com  

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.

Cautionary Note Regarding Forward-Looking Statements

This release includes certain statements that may be deemed to be “forward-looking statements”. Forward-looking statements are subject to risks, uncertainties and assumptions and are identified by words such as expects,” “estimates,” “projects,” “anticipates,” “believes,” “could,” “scheduled,” and other similar words. All statements in this release, other than statements of historical facts, that address events or developments that management of the Company expects, are forward-looking statements. Although management believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance, and actual results or developments may differ materially from those in the forward-looking statements. The Company undertakes no obligation to update these forward-looking statements if management’s beliefs, estimates or opinions, or other factors, should change. Factors that could cause actual results to differ materially from those in forward-looking statements, include market prices, exploration, and development successes, continued availability of capital and financing, and general economic, market or business conditions. Please see the public filings of the Company at www.sedar.com for further information.

Century Lithium Corp. (CYDVF) – A Watershed Moment?


Monday, February 13, 2023

Mark Reichman, Senior Research Analyst, Natural Resources, Noble Capital Markets, Inc.

Refer to the full report for the price target, fundamental analysis, and rating.

Collaboration with Koch. Century Lithium is collaborating with Koch Technology Solutions (KTS) in the application of its proprietary Li-Pro direct lithium extraction process (DLE) at Century’s lithium extraction facility in Nevada.

Li-Pro technology. Koch purchased exclusive rights to theLionex DLE technology, for which Century had licensed, and integrated it into their Li-Pro process. The companies have executed an agreement to test KTS equipment and evaluate features of the Li-Pro process at Century’s pilot plant. While the program is independent from the company’s ongoing feasibility study, KTS will provide an engineering design along with costs for deployment of the DLE portion of the processing plant.


Get the Full Report

Equity Research is available at no cost to Registered users of Channelchek. Not a Member? Click ‘Join’ to join the Channelchek Community. There is no cost to register, and we never collect credit card information.

This Company Sponsored Research is provided by Noble Capital Markets, Inc., a FINRA and S.E.C. registered broker-dealer (B/D).

*Analyst certification and important disclosures included in the full report. NOTE: investment decisions should not be based upon the content of this research summary. Proper due diligence is required before making any investment decision. 

Release – Century Lithium and Koch Technology Solutions Collaborate on Li-Pro™ Process for Commercial Direct Lithium Extraction

Research News and Market Data on CYDVF

February 9, 2023 – Vancouver, Canada – Century Lithium Corp. (TSXV: LCE) (OTCQX: CYDVF) (Frankfurt: C1Z) (“Century Lithium”) is pleased to announce its collaboration with Koch Technology Solutions (“KTS”), a Koch Engineered Solutions (“KES”) company, in the application of the Li-Pro™ process for direct lithium extraction (“DLE”) at Century Lithium’s Lithium Extraction Facility (“Pilot Plant”) in Amargosa Valley, Nevada, USA.

“Century Lithium’s collaboration with KTS and KES has been productive, and we look forward to working together as we broaden our relationship,” said Bill Willoughby, President & CEO of Century Lithium. “Our DLE process in the Pilot Plant is performing very well and we are excited to work with Koch as we advance the Project.”

In March 2022, Century Lithium purchased a license to the Lionex DLE process (“Lionex”) and KTS subsequently acquired exclusive rights to the Lionex technology, which has been integrated into KTS’ Li-Pro™ process. Through an agreement completed February 6, 2023, the companies will work together to evaluate the added features of the Li-Pro™ process at Century Lithium’s Pilot Plant. With the information obtained, KTS will provide engineering for a full-scale deployment of the Li-Pro™ process for Century Lithium’s Clayton Valley Lithium Project (“Project”) located in Esmeralda County, in west-central Nevada.
 

“Century Lithium has done a great job identifying and validating a world-class lithium resource,” said Adam Sackett, President of Koch Technology Solutions. “As the energy transformation accelerates, we are excited to collaborate with them on the path to commercializing Li-Pro™ technology with our expanding set of complementary capabilities.”

As part of the program, certain key components of the Li-Pro™ process will be tested at Century Lithium’s Pilot Plant. KTS will also provide engineering design and costs for the full-scale DLE portion of the processing plant for Century Lithium’s Project. This program is independent from the Project’s ongoing Feasibility Study and will begin upon delivery of KTS equipment to the Pilot Plant. Century Lithium will fund the study, installation, and operation of the equipment at the Pilot Plant, and KTS will provide training and technical support.

About Koch Technology Solutions

Koch Technology Solutions (KTS) is the technology licensing business of Koch Engineered Solutions (KES). KTS creates value for its customers across a growing portfolio of technologies including direct lithium extraction, the polyester value chain, refining industry and 1,4-Butanediol plus its derivatives. KTS combines its exclusive technologies, expertise, and capabilities with those of other KES companies to provide overall solutions to optimize customers’ capital investments and existing manufacturing assets.

About Century Lithium Corp.

Century Lithium Corp. is a Canadian based advanced stage lithium company, focused on developing its 100%-owned Clayton Valley Lithium Project in west-central Nevada, USA. Century Lithium is currently in the pilot stage of testing on material from its lithium-bearing claystone deposit at its Lithium Extraction Facility in Amargosa Valley, Nevada and progressing towards completing a Feasibility Study and permitting, with the goal of becoming a domestic producer of lithium for the growing electric vehicle and battery storage market.

ON BEHALF OF CENTURY LITHIUM CORP.
WILLIAM WILLOUGHBY, PhD., PE
President & Chief Executive Officer

For further information, please contact:
Spiros Cacos | Vice President, Investor Relations
Direct: +1 604 764 1851
Toll Free: 1 800 567 8181
scacos@centurylithium.com
centurylithium.com  

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.

Cautionary Note Regarding Forward-Looking Statements

This release includes certain statements that may be deemed to be “forward-looking statements”. Forward-looking statements are subject to risks, uncertainties and assumptions and are identified by words such as expects,” “estimates,” “projects,” “anticipates,” “believes,” “could,” “scheduled,” and other similar words. All statements in this release, other than statements of historical facts, that address events or developments that management of the Company expects, are forward-looking statements. Although management believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance, and actual results or developments may differ materially from those in the forward-looking statements. The Company undertakes no obligation to update these forward-looking statements if management’s beliefs, estimates or opinions, or other factors, should change. Factors that could cause actual results to differ materially from those in forward-looking statements, include market prices, exploration, and development successes, continued availability of capital and financing, and general economic, market or business conditions. Please see the public filings of the Company at www.sedar.com for further information.

Cypress Development (CYDVF) – Feasibility Study On Track for Mid-Year 2023 Completion; Corporate Name Change


Wednesday, January 25, 2023

Mark Reichman, Senior Research Analyst, Natural Resources, Noble Capital Markets, Inc.

Refer to the full report for the price target, fundamental analysis, and rating.

Corporate name change. Cypress Development’s Board of Directors approved a corporate name change to Century Lithium Corp. which is subject to approval by the TSX Venture Exchange (TSXV). While the TSXV ticker symbol will change, the ticker symbol on the OTCQX will not. Cypress will issue a news release announcing the date that trading under the new name, symbol, and CUSIP number will commence. We think the new name will help increase awareness among investors given that it more closely identifies the company with its mission. 

Feasibility study expected by the end of 2Q 2023. The feasibility study for the Clayton Valley Lithium project is advancing on schedule with completion anticipated by mid-year. On-site infrastructure designs, including mine, processing plant and tailings, and waste storage facilities are completed. Cost and market studies are underway, along with assessments for construction, component lead-time and off-site infrastructure. Efforts are being made to initiate federal, state, and local permitting for the project, along with an evaluation of associated infrastructure.


Get the Full Report

Equity Research is available at no cost to Registered users of Channelchek. Not a Member? Click ‘Join’ to join the Channelchek Community. There is no cost to register, and we never collect credit card information.

This Company Sponsored Research is provided by Noble Capital Markets, Inc., a FINRA and S.E.C. registered broker-dealer (B/D).

*Analyst certification and important disclosures included in the full report. NOTE: investment decisions should not be based upon the content of this research summary. Proper due diligence is required before making any investment decision. 

Release – Cypress Development to Change Name To Century Lithium Corp

Research News and Market Data on CYDVF

January 24, 2023

January 24, 2023 – Vancouver, Canada – Cypress Development Corp. (TSXV: CYP) (OTCQX: CYDVF) (Frankfurt: C1Z1) ( “Cypress” or “the Company”) announces that the Board of Directors has approved a name change of the Company from Cypress Development Corp. to Century Lithium Corp.

The Company will also change the ticker symbol upon which it trades on the TSX Venture Exchange (“TSXV”).  The Company will issue a further news release announcing the date that trading under the new name, symbol and CUSIP number will commence.  The name change remains subject to TSXV approval.

About Cypress Development Corp
Cypress Development Corp. is a Canadian based advanced stage lithium company, focused on developing its 100%-owned Clayton Valley Lithium Project in Nevada, USA. Cypress is in the pilot stage of testing on material from its lithium-bearing claystone deposit and progressing towards completing a Feasibility Study and permitting, with the goal of becoming a domestic producer of lithium for the growing electric vehicle and battery storage market.

ON BEHALF OF CYPRESS DEVELOPMENT CORP.

WILLIAM WILLOUGHBY, PhD., PE

President & Chief Executive Officer

For further information, please contact:

Spiros Cacos | Vice President, Investor Relations
Direct: +1 604 764 1851 | Toll Free: 1 800 567 8181 | Email scacos@cypressdevelopmentcorp.com
www.cypressdevelopmentcorp.com

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.

Release – Cypress Development Provides Progress Update on Feasibility Study And Lithium Extraction Facility

Research News and Market Data on CYDVF

January 23, 2023

January 23, 2023 – Vancouver, Canada – Cypress Development Corp. (TSXV: CYP) (OTCQX: CYDVF) (Frankfurt: C1Z1) (“Cypress” or “the Company”) is pleased to provide a progress update on its ongoing Feasibility Study being conducted on the Company’s Clayton Valley Lithium Project (“Project”) near Silver Peak, Nevada, and on its operational Lithium Extraction Facility (“Pilot Plant”) in Amargosa Valley, Nevada.

Highlights

  • The Pilot Plant continues to function as designed, working to optimize the Project’s flowsheet. The Plant leaches lithium-bearing claystone material, through to the production of concentrated lithium solution using the Company’s Direct Lithium Extraction (“DLE”) process.
  • Additional piloting runs will take place at Saltworks Technologies, Inc. following the successful production of lithium carbonate (“Li2CO3”) from the Pilot Plant’s concentrated lithium solutions.
  • The Project’s Feasibility Study is on schedule and is continuing to advance toward an anticipated second quarter 2023 completion.
  • Arrangements are proceeding to initiate federal, state, and local permitting for the Project, with compilation of data and evaluation of related infrastructure, including access, water, and power supply corridors.
  • Ahead of the Feasibility Study and permitting, Cypress management is assessing personnel needs and future Project financing opportunities and structures, which may include government grants and loans.

Pilot Plant

Cypress continues to conduct testing at its Pilot Plant with the support of del Sol Refining, Inc. Since its start-up, the Pilot Plant has operated in 28 cycles of continuous 24/7 operation, with minimal down-time and maintenance matters. The test work was conducted using multiple configurations and equipment to best replicate the Project flowsheet. In the testing to date, nearly 10,000 samples of solutions, solids and precipitates have been collected and analyzed. Other data collection, including recording of flow rates and physical conditions at key sample points throughout the Pilot Plant, has been conducted, with particular attention to the DLE section of the Pilot Plant to develop the Project’s mass-balance calculations, and to finalize the flowsheet for the Feasibility Study.

Pilot Plant testing has achieved targets in most areas, including operating with 100% recycled solutions. Specific challenges were addressed with sufficient results to aid in the completion of the Feasibility Study. Further testing in 2023 is planned to confirm the overall process, continue to demonstrate the flowsheet, and produce samples of Li2CO3. Additional 1000-liter lots of concentrated lithium solution from the DLE section of the Pilot Plant will be shipped to Saltworks Technologies, Inc, in Richmond, B.C., Canada by month end.

2023 plans for the Pilot Plant include testing alternate reagents and equipment, which may include identification of potential by-products, and ways to enhance impurity removal and the DLE process area. Additional space within the Pilot Plant building has been prepared for this work.

Feasibility Study

The Feasibility Study is advancing on schedule, with completion anticipated by mid-year. On-site infrastructure designs, including, mine, processing plant, and tailings and waste storage facilities are completed. Cost estimating and market studies are underway, along with assessments for construction, component lead-time and off-site infrastructure. Completion of the Feasibility Study will then await integration of the design and cost estimates for the acid plant underway by thyssenkrupp nucera.

In addition, Cypress management is assessing personnel needs and future Project financing opportunities and structures, which may include government grants and loans.

About Cypress Development Corp

Cypress Development Corp. is a Canadian based advanced stage lithium company, focused on developing its 100%-owned Clayton Valley Lithium Project in Nevada, USA. Cypress is in the pilot stage of testing on material from its lithium-bearing claystone deposit and progressing towards completing a Feasibility Study and permitting, with the goal of becoming a domestic producer of lithium for the growing electric vehicle and battery storage market.

ON BEHALF OF CYPRESS DEVELOPMENT CORP.
WILLIAM WILLOUGHBY, PhD., PE
President & Chief Executive Officer

For further information, please contact:
Spiros Cacos | Vice President, Investor Relations
Direct: +1 604 764 1851 | Toll Free: 1 800 567 8181 | Email scacos@cypressdevelopmentcorp.com
www.cypressdevelopmentcorp.com  

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THE CONTENT OF THIS NEWS RELEASE.

Cypress Development (CYDVF) – Nevada Claystone Projects Could Be a Key Component of the EV Battery Supply Chain


Tuesday, January 17, 2023

Mark Reichman, Senior Research Analyst, Natural Resources, Noble Capital Markets, Inc.

Refer to the full report for the price target, fundamental analysis, and rating.

Lithium from Nevada claystone. Cypress Development is advancing its 100%-owned Clayton Valley Lithium Project in Nevada. Cypress intends to mine claystone, produce a high-grade lithium concentrate solution using a chloride leach process, and apply a licensed direct lithium extraction process based on ion-exchange to produce lithium carbonate suitable for battery producers supplying the growing electric vehicle and battery storage market.

Funding from the U.S. Department of Energy. The U.S. Department of Energy’s (DOE) Loan Programs Office (LPO) recently offered a conditional commitment to lend up to US$700 million to develop Ioneer’s (Nasdaq: IONR) Rhyolite Ridge lithium-boron mining project in Nevada. In our view, the loan reflects the U.S. government’s commitment to assure domestic supplies of lithium and other critical minerals for the growing electric vehicle battery market.


Get the Full Report

Equity Research is available at no cost to Registered users of Channelchek. Not a Member? Click ‘Join’ to join the Channelchek Community. There is no cost to register, and we never collect credit card information.

This Company Sponsored Research is provided by Noble Capital Markets, Inc., a FINRA and S.E.C. registered broker-dealer (B/D).

*Analyst certification and important disclosures included in the full report. NOTE: investment decisions should not be based upon the content of this research summary. Proper due diligence is required before making any investment decision. 

Cypress Development (CYDVF) – Details Emerge as the Clayton Valley Feasibility Study Takes Shape


Friday, October 28, 2022

Mark Reichman, Senior Research Analyst, Natural Resources, Noble Capital Markets, Inc.

Refer to the full report for the price target, fundamental analysis, and rating.

Another box checked. Cypress Development selected thyssenkrupp nucera USA, Inc. to provide the design and engineering for the chlor-alkali plant as it advances its Clayton Valley Lithium Project in Nevada. The chlor-alkali plant will enable the project to produce two key reagents, hydrochloric acid and sodium hydroxide, required for processing lithium-bearing claystone through to a lithium carbonate product. The company’s selection of thyssenkrupp nucera represents another step towards completion of the feasibility study in the second quarter of 2023.

Feasibility study is taking shape. Work on the feasibility study commenced in March under the direction of Wood PLC and is advancing as planned. Wood, along with support from others, has completed or is nearing completion of several items, including resource and reserve estimates, mine plan, processing plant design, and tailings and waste storage facilities.